By Dan Klepal
Enquirer staff writer
CROSBY TWP. - The most difficult and dangerous job at the $4 billion Fernald nuclear cleanup in northwest Hamilton County has begun.
The project, 12 years in the making, started Tuesday when crews at the long-closed uranium plant started pumping highly radioactive waste out of two concrete storage silos and into temporary metal tanks, which will hold the material until it is mixed with concrete and shipped across country for disposal.
In addition to the pipes used to pump the material from the silos into the tanks, a separate pipe system continuously cleans the air inside the silos because of the huge amounts of radon gas the waste generates.
There are three "silos" at the sprawling, 1,050-acre Fernald site. Silos 1 and 2 hold the most dangerous waste. A third silo holds radioactive powder.
Crews began pumping water into the two silos with the clay-like waste last week.
Jeff Wagner, a spokesman for the government's contractor performing the work, said the work on the $400 million silos project will ultimately define the success or failure of the entire cleanup.
"This is the most significant step we've taken in the project," Wagner said. "The silos will define when the site will ultimately be closed. Today is a big step in completing not only the silos, but ultimately taking those final steps we need for closure."
The government has set a 2006 deadline to finish the entire cleanup, which includes removing millions of tons of radioactive dirt, building debris, cleaning underground water and removing waste from the three silos. That deadline is in jeopardy because Nevada has threatened to sue to keep the waste from being buried in the desert near Las Vegas. That issue is still unresolved, but it will take about four months to empty the two silos.
Lisa Crawford, a nearby resident of the plant and long-time observer of the cleanup for a citizen's group that sued to get the cleanup started, said it's a scary project.
"This is the worst stuff out there," Crawford said. "So we're all a little nervous. We want them to do this cautiously, and we'll be paying very close attention."
The work of emptying the powdery waste from Silo 3 was supposed to begin months ago, but has been delayed because of the threatened lawsuit.
E-mail dklepal@enquirer.com
TOP STORIES
Elder students pay respects to classmate
Boat-crash driver gets 10 years
Newport officer charged in DUI
Nader booted off Ohio ballot over petitions
Fernald finally opens the pipe
Officer cleared in force charge
ELECTION 2004
Negative buzz from candidates could hurt region
Cost of Bush rally? Amount likely unknowable
Coroner candidates spar
Election 2004 page
IN THE TRISTATE
Wider I-275 stretch starts in 2007
Students vie for scholarships
Man, 32, indicted in fatal car crash
Buchanan, Cuomo to debate at Miami
Jail deal prompts emergency meeting
Fairfield studies citywide smoke ban
Volunteers head to Florida
Lakota students may get shuffled
local news briefs
Mason delays zone change
Family fees going up $75
Neighbors briefs
Voter-card rules cause concern
Miami student charged with rape
Ohio honors 102 schools
Public safety briefs
Mental-health board trims
Judge supports welfare recipients
ENQUIRER COLUMNISTS
Businesses pass half-century test
LIVES REMEMBERED
Nancy Haigwood, 69
KENTUCKY STORIES
Imported medicine: A budget healer?
N. Ky. news briefs
Expo is the Homearama of sediment and erosion
Kenton medical debate ongoing
School bus driver gives hunter a ride - 'So?' residents say
Ky. 17 plans near completion